GOTEMBA
Electrical
SHIZUOKA (Japan) | jul 24 - dic 24
Country:
JAPAN (Shizuoka)
Final Customer:
Vena Energy Japan
THJ Customer:
SRC Construction Japan
THJ SOW STATUS: Finished
Duration: 6 months
DC TOTAL CAPACITY (MWp): 2
DC THJ SCOPE (MWp): 2
INSTALLATION TYPE: PV Fix-tilt
PROJECT CATEGORY: Retrofit
PROJECT HIGHLIGHTS: Operating PV plant retrofit · Replacement of stolen AC cables · Aluminium conductor installation · Repair of cable support infrastructure
SCOPE SUMMARY: DC main Copper cable replacement to Aluminium
MAIN EQUIPMENT MECH: «Structure: Fix-tilt 4Hx7 | Modules: 335 W»
MAIN EQUIPMENT ELEC: «String inverters | Cables: Solar cable ( 3,5 mm2) / AC (600 V Al 250,325 & 400 mm2)»